FIRST CONSTRUCTION UPDATE

Saturday, October 26, 2013

Find out what's happening in Montclairwith free, real-time updates from Patch.

Milling PORTIONS of the following roadways

  • Cedar Avenue – High Street to Orange Road
  • Harrison Avenue – Cedar Avenue to Oak Street
  • Claremont Avenue – Highland Avenue to Prospect Avenue
  • Claremont Avenue – Upper Mountain Avenue to North Mountain Avenue

MILLING COMPLETE - ALL PORTIONS OF CEDAR AVE., HARRISON AVE., CLAREMONT AVE

Monday, October 28, 2013

Milling PORTIONS of the following roadways

  • Upper Mountain Avenue – Edgewood Road to Claremont Avenue
  • Upper Mountain Avenue – Berkeley Place to Bellevue Avenue

Tuesday, October 29, 2013

Milling PORTIONS of the following roadways

  • Upper Mountain Avenue – Edgewood Road to Claremont Avenue
  • Upper Mountain Avenue – Berkeley Place to Bellevue Avenue
  • Bellevue Avenue – Valley Road to 100 Feet East of Northview Avenue

Wednesday, October 30, 2013

Milling PORTIONS of the following roadways

  • Bellevue Avenue – Valley Road to 100 Feet East of Northview Avenue

Paving PORTIONS of the following roadways

  • Cedar Avenue – High Street to Orange Road
  • Harrison Avenue – Cedar Avenue to Oak Street
  • Claremont Avenue – Highland Avenue to Prospect Avenue
  • Claremont Avenue – Upper Mountain Avenue to North Mountain Avenue

Thursday, October 31, 2013

Paving PORTIONS of the following roadways

  • Claremont Avenue – Highland Avenue to Prospect Avenue
  • Claremont Avenue – Upper Mountain Avenue to North Mountain Avenue
  • Upper Mountain Avenue – Edgewood Road to Claremont Avenue
  • Upper Mountain Avenue – Berkeley Place to Bellevue Avenue
  • Bellevue Avenue – Valley Road to 100 Feet East of Northview Avenue